3D model of a METALOQ module frame
Documentation

DfMA: making and shipping

From steel coil to a module set on site.

In brief

DfMA implementation for licensees

We do more than document this method. We implement it with you. METALOQ offers DfMA implementation as a service to licensees, so your team starts with a working system instead of building one from scratch.

  • A closed catalogue. We set up your list of approved components, each with its cost, source, lead time and fire rating on record.
  • A library of standard details. Every detail is resolved once using catalogue components, then reused, not redrawn.
  • One naming system. The same part names run through design, purchasing and the shop floor.
  • Modules and buildings configured, not redesigned. Cost, mass and lead time are known from the first sketch.
  • Cut files and bills of materials from one model. Nothing is re-entered by hand, and production is tracked against what was issued.

Talk to us about DfMA implementation

Designed for manufacture

An architect usually works from the site down to the detail. Design for manufacturing and assembly reverses that order: it starts with standard parts and details and builds up to the finished building. Cost, mass and lead time are known at every step, from component to module to building.

Manufacturing

Six photos: steel coil, laser cutting, brake forming, welding, a machined connector and a stacked module frame
Coil, laser, brake, weld, component, module.
  • Coil cutting. The model drives the laser table, which cuts every slot, hole and connection into the steel.
  • Brake forming. Columns and rim beams are formed on large press brakes.
  • Component welding. Stiffeners, end plates and connection plates are welded on.
  • Specialty connectors. Daggers and dogbones are machined into high-precision parts.
  • Joists. Joists are roll-formed with standard tooling.

Fabricated frames are checked before they leave the shop, and a sample of frames is pre-assembled to prove the fit.

Certifications

FabricatorCWB certified, CSA W47.1 Division 2
WeldersCWB qualified
Structural plateMill certified, CSA G40.21 44W / 50W and ASTM A36
Galvanized sheetMill certified, ASTM A653 with G90 coating

Packing and shipping

The frame is knocked down for shipping. The steel for up to 12 modules is flat-packed into a single 40-foot container, including rim beams, columns, joists, bracing, clamps and fasteners.

A 40-foot container packed with flat-packed frame components

Storage, transport and setting

Finished modules are shrink-wrapped against air and moisture, then delivered by truck, barge or rail. The daggers double as hoisting and lashing hardware. On site, each module is lowered onto the daggers of the one below and bolted from inside the unit or through a small opening outside.

A wrapped METALOQ module on a flatbed truck on a highway
Transport
A crane setting a module onto a mid-rise building under construction
Setting

Chapter 7 in full

METALOQ Documentation v1.0, pages 50–53. Select a page to enlarge it.

7 DfMA

7.1 Design

7 DfMA, page 50
Page 50Enlarge
Read page 50 as text

Fig. 7.1 — A diagram showing the five tiers of assembly, from a purchased component to a full building.

Fig. 7.2 — A diagram showing how the kit of parts forms increasingly complex assembly trees.

CHAPTER

DfMA

HOW THIS CHAPTER IS ORGANIZED

§7.1 Design sets out the design method and the naming convention, from the parts to the whole. §7.2 Manufacturing is the fabrication logic, the tolerance regime and the QA checkpoints. §7.3 Logistics covers storing the modules, shipping them to site and setting them.

7. 1 Design

Design Sequence. An architect typically works from the site down: city, massing, plan, assembly, and finally detail. Design for Manufacturing and Assembly (DfMA) reverses this sequence. A factory requires standardized parts and systems, both for production familiarity and to maintain organizational control. Designing for manufacture inverts the usual order, proceeding from the details up to the completed building.

Factory-based construction favours repeatability, built on a complete understanding of the supply chain and assembly process. Before a project begins, every component has known properties, and these components assemble into progressively larger groups. This eliminates unknowns, which are difficult to accommodate on an assembly line. Cost, mass, lead time, and tolerance accumulate through the same hierarchy as the geometry: component → detail → subassembly → module → building → complex (see facing page). Certainty builds incrementally through this hierarchy, rather than being determined only at the final stage.

STAGE WHAT IT IS THE CERTAINTY IT ADDS

1 COTS Components Off The Shelf: a closed catalogue of approved materials and products.

Every item used in a building has already been vetted, priced, and sourced.

2 COTS data Each catalogue item carries its MRP record: cost, source, supply chain, lead and install time, fire rating, fastening.

A component’s properties are known before it is used, so any assembly containing it can be costed and scheduled.

3 DOTS Details Off The Shelf: a library of standard details, each resolved using only COTS items.

Each detail is resolved once, then selected from the library and not redrawn. A new condition is added to the library.

4 Module The module types (stair, elevator, unit, and service) are configured from the COTS and DOTS above.

A module is configured from existing details, not designed from new. Its cost, mass, tolerance, and lead time are the sum of its details.

5 Building Buildings stacked from the product line of modules, within the constraints the line already carries.

Massing options compare on real cost and schedule from the first sketch, because every option is made of known modules.

This strategy enables automation in part design, purchasing, and assembly tracking. Implementation requires a standard naming system. METALOQ recommends that a trigram system, as outlined in the Glossary, be used consistently throughout the design, purchasing and manufacturing process.

6 Cut files The fabrication model of every component in the project, issued from the model the design was configured in.

The cut files are issued directly from the design model, so there is no translation step in which the two can diverge.

7 BOM Quantities, nomenclature, workflows and revisions output from that same model.

The bill is a product of the model, never a parallel document that can disagree with it.

8 Tracking Production and revisions monitored against the issued BOM.

Estimated cost is replaced by actual cost, and the record of this project becomes the COTS data for the next project.

DESIGN RULE Two representations, one record

Every object in the chain has two representations: lightweight for configuration, massing, and coordination, and full detail for fabrication. They are two views of one record, not two models.

7.2 Manufacturing

7.2.1 Manufacturing Logic

7.2.2 Tolerance & Fit-Up

7.2.3 Quality Assurance

7.2 Manufacturing, page 51
Page 51Enlarge
Read page 51 as text

1 C OI L

2 LASER

3 BRAKE

4 W E LD

5 COMPONENT

6 MODULE

7. 2 Manufacturing

METALOQ components are manufactured in True Volumetric’s specialized steel fabrication shop. The following sections describe the manufacturing logic, tolerance, and quality assurance rules that apply to every frame variant. Comprehensive fabrication shop work instructions for each individual variant are available by contacting True Volumetric.

Manufacturing Logic

METALOQ is fabricated with customized steel tooling and fabrication methods. The manufacturing model has five defining stages:

• Coil Cutting: The frame structure is fabricated from standard steel coil in various thicknesses. The SolidWorks model drives the laser-cutting table, which cuts the coil into parts including columns and beams. At this stage all the slots, holes, and connections are cut into the sheet.

• Brake-Forming: Columns and rim beams are formed on large press brakes into cold-formed steel (CFS) structural shapes.

• Component Welding: Web stiffeners, top and bottom end plates, and connection plates are welded on to complete each component.

• Specialty Connectors: Daggers and dogbone plates are cut and CNC-machined into high-precision parts.

• Joists: Joists are made with standard roll-forming and press-brake tooling, which also forms the dimple.

Tolerance & Fit-Up

The tolerance regime maintains the zero-clearance requirement of §1.3. A module’s external dimension is its grid dimension, so fabrication tolerance cannot be absorbed at a later stage.

• Critical Datums: Every toleranced dimension is measured from the 0-0-0 datum, not from one component to the next.

• Precision-Bearing Conditions: Dagger sockets and dogbone seats have tighter tolerances than the members they are located on.

• Fit-Up Logic: Open sections provide wrench and hand-hole access. No connection is captured or blind.

• Accumulation Control: Datum-referenced dimensioning prevents tolerance from accumulating over the building height.

Quality Assurance

QA verifies that fabricated frames meet the tolerance regime before they leave the shop. The QA/QC plan defines inspection checkpoints across the flow:

• Material QA: Mill test reports are retained for each component (see Chapter 3).

• Weld Inspection: Every welded subassembly is visually inspected, with NDT sampling on structural welds.

• Dimensional Inspection: First-article inspection and ongoing sampling are measured against the 0-0-0 datum.

• Coating Inspection: Galvanizing is verified to ASTM A123 (85 µm minimum).

• Part Tracking: Every part is identified by its METALOQ part number (see Glossary). Standard parts carry the same number on every project; project parts add the complex, building and module, so each one can be traced from the shop floor to its place in the building.

• Pre-Ship Checkpoint: The completeness of the knocked-down (KD) kit and the pallet QA are checked before release.

Packing & Shipping

Packing & Shipping, page 52
Page 52Enlarge
Read page 52 as text

PACKING & SHIPPING

Container Packing

The frame is knocked-down for shipping. The steel for up to 12 modules is flat- packed into a single 40-foot container. This includes all the required components: the rim beams, columns, floor and ceiling joists, bracing, clamps and fasteners.

OFF THE MODEL

Members are stacked by type on steel skids. Every layer lands on dressed SPF spacers (the pale timber visible running through the stacks) rather than on the piece below it, so no steel bears directly on steel until the frame is assembled.

• Container: 40 ft high-cube, open top. The body measures 40 ft 0 in × 8 ft 0 in. • Dunnage: 250 dressed SPF 2×4 spacers, on 6×6 and 4×4 HSS steel skids.

7.3 Logistics

7.3.1 Storage

7.3.2 Transport

7.3.3 Setting

7.3 Logistics, page 53
Page 53Enlarge
Read page 53 as text

7. 3 Logistics

This section covers the three stages of handling METALOQ-based volumetric modules that are fitted out and ready to send to site:

• Storage at the plant

• Transport to site

• Setting on site

Storage

Volumetric modules are wrapped in heavy-duty shrink wrap that seals out air and moisture. Depending on climate and duration, the protection should be designed with a building science engineer so that finishes are protected from humidity and temperature fluctuations, which can cause finish damage and mould. Desiccant packs, relative humidity and temperature monitors and/or rotating inspections are commonly used to ensure the contents are climate-controlled. The same wrap protects the module during transport.

Transport

Completed METALOQ-based modules are stored in a yard until they are shipped to the job site. The three delivery modes are truck, barge, and rail. The mode is selected for each project according to haul distance, module envelope, and site access. Bracing must be designed to resist hoisting and transportation loads, which are often more severe than the loads a building resists in service. Bracing that takes these dynamic loads into account can reduce or eliminate cracking, commonly at drywall corners. The METALOQ design team can help your engineering and logistics team with approved handling methods.

• Transport-Only Bracing: Where a barge, road, or rail voyage governs over the in-service seismic demand, additional bracing is fitted for transport duty only. Transport-only bracing may be released on site once the module is set, at the owner’s option, so it is not carried forward as superfluous in-service steel.

• Hoist Points: A METALOQ-based module can be lifted in various ways: by coordinated lift devices, a factory crane with straps or, most commonly, by the daggers. Daggers used for lifting are installed at the top of the module and have unthreaded holes for a shackle.

• Lash Points: The dagger array doubles as the hoisting and lashing hardware for transport and placement. On truck, rail or barge the daggers are installed face-down at the base and tie the load down to dunnage that spreads the load across the deck. The lashing should be engineered collaboratively by the METALOQ engineer and the transportation team.

Setting

The set sequence must be designed around climate, temporary waterproofing, crane deployment and shipping sequence. The first modules connect to one of several starting points: foundation, slab or podium. Once a module has landed, the dagger is installed and/or torqued to the connection point. At higher levels, the dagger connection can be made from inside the module through a drywall access hole, patched after the set, or from the front elevation through a similar access hole.

Every module carries a lightweight roofing membrane that is designed to remain in the floor assembly after setting. The hoisting daggers at the top of the module can be removed and the temporary waterproofing sealed. An additional strip of waterproofing can be flipped over and sealed to its neighbour.

There are two ways to stack modules: by level and in steps. Setting a full level is the most robust: facing modules are set on either side of the double-loaded corridor, then a corridor frame caps and waterproofs the corridor between them. At the end of each day, the exposed side of the last module must be protected from rain. The step method reaches the roof sooner, which reduces roof waterproofing, and the crane advances down the building’s length with the set; but it increases the side waterproofing required.