Ideas for a modular factory. Julian Bowron, World of Modular Europe, Brussels 2024.

Presentation

Select a slide to enlarge it.

Scaling Modular Construction, slide 1
Slide 1 of 86Enlarge
Read slide 1 as text

Scaling Modular Construction

with

DfMAD

Author: Julian Bowron, CTO, METALOQ

Copyright 2024

METALOQ

Kit Frames for Modular Builders * Modular Frame Connection Technology

Autonomous Modular Building Systems * Manufacturing Technology

Governments, humanitarian agencies and the AEC industry are searching for solutions to the multi-million-unit global hou, slide 2
Slide 2 of 86Enlarge
Read slide 2 as text

Governments, humanitarian agencies and the AEC industry are searching for solutions to the multi-million-unit global housing shortage

Despite the huge need, most modular companies produce less than 2,000 modules per annum.

A small number produce 8,000 or more every year.

What are the success factors for high-volume modular production?

Success Stories, slide 3
Slide 3 of 86Enlarge
Read slide 3 as text

Success Stories

A number of companies in NA, the EU and the ME have achieved significant production volumes

Images: Tide Construction, 20,000+ units delivered

Image: DORCE Modular Workforce camp for 25,000 workers, slide 4
Slide 4 of 86Enlarge
Read slide 4 as text

Image: DORCE Modular Workforce camp for 25,000 workers

Image: KARMOD Modular Refugee Housing for 17,000 Persons, slide 5
Slide 5 of 86Enlarge
Read slide 5 as text

Image: KARMOD Modular Refugee Housing for 17,000 Persons

Image: Spacemaker KSA Workforce Housing for 25,000 Persons (x 2), slide 6
Slide 6 of 86Enlarge
Read slide 6 as text

Image: Spacemaker KSA Workforce Housing for 25,000 Persons (x 2)

Images: VBC, slide 7
Slide 7 of 86Enlarge
Read slide 7 as text

Images: VBC

6,000 + apartments, 20+ buildings to date

What are the factors that are limiting the growth of most modular builders?, slide 8
Slide 8 of 86Enlarge
Read slide 8 as text

What are the factors that are limiting the growth of most modular builders?

“10 Great Evils”

….that elevate costs, slow production and reduce volumes

Evil #1: Performative Modular Construction, slide 9
Slide 9 of 86Enlarge
Read slide 9 as text

Evil #1: Performative Modular Construction

Is it desirable to make and store enough modules so that an anthill of workers can video the erection of a modular building in 7 days?

Evil #1 cont…., slide 10
Slide 10 of 86Enlarge
Read slide 10 as text

Evil #1 cont….

3D printing stylish single-family homes with concrete is cool, but it’s not going to solve the housing crisis

Evil #2: “Go Big or Go Home”, slide 11
Slide 11 of 86Enlarge
Read slide 11 as text

Evil #2: “Go Big or Go Home”

Spending $300 million dollars on a factory “right out of the gate”

…..with payroll, operating costs and debt to match ….

leads to financial pressures,

bad decision making

and dilution of founder’s equity

Evil #3: Unnecessary Complexity, slide 12
Slide 12 of 86Enlarge
Read slide 12 as text

Evil #3: Unnecessary Complexity

“Mass Customization” results in excessive variants and odd details, leading to increased costs at all stages in the modular building process, from design to supply chain, manufacturing, erection and completion

Evil #1:

Unnecessary Complexity

Evil #4:, slide 13
Slide 13 of 86Enlarge
Read slide 13 as text

Evil #4:

Inaccuracy

Sloppy work leads to poor building performance and higher costs at all phases in the manufacturing, assembly and completion process

Evil #5:, slide 14
Slide 14 of 86Enlarge
Read slide 14 as text

Evil #5:

Incomplete Detailing

Schematic design followed by resolution of details at the site is expensive and slow

Evil #6: Excess Inventory of WIP and Product, slide 15
Slide 15 of 86Enlarge
Read slide 15 as text

Evil #6: Excess Inventory of WIP and Product

Storing modules waiting for assembly ties up capital, increases handling costs and creates storage costs and risks

Evil #6: Example:, slide 16
Slide 16 of 86Enlarge
Read slide 16 as text

Evil #6: Example:

Unitarily-welded module frames create WIP 2x, 1st by increasing TAKT times for frames, and again by creating a production bottleneck…

Completed, but stranded = WIP

Accessible, but arc-on-time limited

Evil #7: Fragile Supply Chains, slide 17
Slide 17 of 86Enlarge
Read slide 17 as text

Evil #7: Fragile Supply Chains

Extended supply chains are inherently fragile and prevent builders from achieving JIT inventory management

Even local supply chains can be disrupted by payment and contract issues, inadequate inventory, long lead times and “Black Swan Events” (Suez Canal, COVID etc.)

Evil #8: Inefficient Factory Design, slide 18
Slide 18 of 86Enlarge
Read slide 18 as text

Evil #8: Inefficient Factory Design

Example:

Modules placed end to end, combined with awkward material delivery routing

= extended TAKT times and

less efficient utilization

of space and capital

Evil #9: Too Much Innovation, slide 19
Slide 19 of 86Enlarge
Read slide 19 as text

Evil #9: Too Much Innovation

Do you want to do R&D…..or do you want to complete buildings?

Evil #10:, slide 20
Slide 20 of 86Enlarge
Read slide 20 as text

Evil #10:

Fragile Pipeline

The products of some modular builders can’t gain required approvals,

are too expensive to build,

or lack a compelling market advantage,

leading to a fragile

order pipeline

What the 10 Evils have in common is a lack of:, slide 21
Slide 21 of 86Enlarge
Read slide 21 as text

What the 10 Evils have in common is a lack of:

Design

for

Manufacturing Assembly and Distribution

DfMAD

Owners / investors control the financial resources entrepreneurs need to fuel growth. Many investors have been convinced, slide 22
Slide 22 of 86Enlarge
Read slide 22 as text

Owners / investors control the financial resources entrepreneurs need to fuel growth. Many investors have been convinced to fund modular startups, only to find profitability elusive.

Product Designers and Plant Managers are tasked with ensuring their products are needed and plants turn a profit.

This necessitates a ruthless focus on relevance and efficiency.

Getting it Right…., slide 23
Slide 23 of 86Enlarge
Read slide 23 as text

Getting it Right….

Success Factor Categories

Product Design:, slide 24
Slide 24 of 86Enlarge
Read slide 24 as text

Product Design:

Can your product be made quickly, inexpensively and easily with COTS materials and technology?

Supply Chain:

Is it JIT? Or is there excess inventory with high costs?

Standardisation vs. Customisation:

Have your designers eliminated excess module variants?

Factory Design:, slide 25
Slide 25 of 86Enlarge
Read slide 25 as text

Factory Design:

Does the plant use capital and space efficiently?

WIP and Factory Logistics:

Are TAKT times and WIP inventory minimized?

Sitework:

Is building assembly and stitching streamlined?

Customer Relationships:

Is product uptake guaranteed?

Modular Manufacturing Metrics, slide 26
Slide 26 of 86Enlarge
Read slide 26 as text

Modular Manufacturing Metrics

The Modular Building Industry is NOT the automotive industry

Auto plants = 2m+ sm (20m sf) producing 500k+ cars / annum = >$10b

500k / 365 = 1370 cars / day = 1 car / minute

Cars have 30,000+ parts and 4000+ SKU’s

So the line never stops, nothing goes in to a car that hasn’t been thoroughly pre-qualified

2,000 modules / 365 = 5 modules / day = 1 module / 5 hours = A production ratio of 1:300 ratio compared to a car plant!

Modules have ~4,000 parts with ~350 SKU’s

Benchmark Material Costs, slide 27
Slide 27 of 86Enlarge
Read slide 27 as text

Benchmark Material Costs

Materials to fabricate a 35 sm module with kitchen, WC, windows and doors:

Low spec, non-stackable temp housing = <$10,000

High end, stackable, to Eurocode / IBC = $40,000+

Range: $280 - $1150/ psm based on application

Material costs are internationalized (Impacts of tariffs NIC!)

Materials costs are common to all producers and are not a good means to create a competitive advantage

Benchmark Labour Costs, slide 28
Slide 28 of 86Enlarge
Read slide 28 as text

Benchmark Labour Costs

Hours to produce 1 x 35 sm module = 180-350 hrs = 5-10 hrs / psm

Labour cost = $6 - $40 / hr (Asia vs. Europe)

Cost / labour / 35sm module = $1,050 - $14,000 (!)

Required hours typical = ~240 x 2,000 units = 480,000 hrs / year

480,000 / 2,000 hours = 240 production workers = $7,200 / module

Labour cost and productivity for a mature producer are common to each market so aren’t a good place to look for margin either

Design costs, material costs, JIT supply chains, and factory layouts are highly interrelated…, slide 29
Slide 29 of 86Enlarge
Read slide 29 as text

Design costs, material costs, JIT supply chains, and factory layouts are highly interrelated…

A complete COTS list with a high level of supply certainty and logistical detail is essential to maintaining smooth production flow……

To achieve this, the parametric model of the product and the corresponding instruction received on the shop floor must align 100%, and data currency must be meticulously maintained

Standardization VS. Customization, slide 30
Slide 30 of 86Enlarge
Read slide 30 as text

Standardization VS. Customization

Architectural design % of one-off conventional construction = 4% arch. + 1% - 2% eng. = 5% - 6% (up to 10% for feature buildings)

Design as % of modular construction for a one-off project is higher, by the 10 th project, design cost should drop to ~1%

360 modules x 35 sm x $2,000 = $25m project x 5% = $1,250,000 / @ $75 / hr = 16,666 hours @ 2000 hrs / annum = 8 person years !

$1,250,000 / 360 = $3,472 / module (!)

An excess of variants and SKU’s increases time and costs through the entire sales, contract, design, procurement, shop i, slide 31
Slide 31 of 86Enlarge
Read slide 31 as text

An excess of variants and SKU’s increases time and costs through the entire sales, contract, design, procurement, shop instruction, manufacturing, sitework and commissioning process……

…..and there is no silver-bullet software or robotic workcell that has successfully solved that problem!

Standardization is a means to create margin

What is the impact of the factory layout on the productivity of a, slide 32
Slide 32 of 86Enlarge
Read slide 32 as text

What is the impact of the factory layout on the productivity of a

modular plant?

How is scalability achieved?

Let’s examine the issues……

Understanding modular production capacity:, slide 33
Slide 33 of 86Enlarge
Read slide 33 as text

Understanding modular production capacity:

Size of assembly bays and plants

Modules in production:

10m x 4m = 40 sm x 3 = 120sm

Floor area required: 378 sm

378 / 120 = Ratio of ~3:1

A ratio of 2.5:1 is possible if the modules are longer, 2:1 is possible if modules are longer and spacing is tightened

4m

4m

4m

3m

3m

3m

4m

10m

4m

18m

21m

Modules in production = 40 sm x 8 = 320 sm, slide 34
Slide 34 of 86Enlarge
Read slide 34 as text

Modules in production = 40 sm x 8 = 320 sm

Assembly area required = 56m x 18m = 1008 sm

Ratio of assembly area to module area = ~ 3: 1

18m

56m

Modules in production = 40 sm x 8 = 320 sm, slide 35
Slide 35 of 86Enlarge
Read slide 35 as text

Modules in production = 40 sm x 8 = 320 sm

Assembly area required = 46m x 13m = 598 sm

Ratio of assembly area to module area = <2: 1

NB: Containers don’t do well in either output-per-area and WIP inventory metrics, as vertical to horizontal area ratio is inherently poor and cutting / rework is time-consuming

13m

46m

Dense production configuration @ RCM Modulaire, PQ, Canada, slide 36
Slide 36 of 86Enlarge
Read slide 36 as text

Dense production configuration @ RCM Modulaire, PQ, Canada

3-level production with “toaster” wall feed @ RCM Modulaire, slide 37
Slide 37 of 86Enlarge
Read slide 37 as text

3-level production with “toaster” wall feed @ RCM Modulaire

Product Size / Speed Impact: Bigger modules moving faster increases output >3x, slide 38
Slide 38 of 86Enlarge
Read slide 38 as text

Product Size / Speed Impact: Bigger modules moving faster increases output >3x

Production time = 5 days x 10 bays = 2 modules x 350 sq ft / 5 days = 700 sf / week

Production time = 3 days x 10 bays = 3.3 modules x 350 sq ft / 5 days = 1,155 sf / week

Production time = 5 days x 10 bays = 2 modules x 700 sq ft / 5 days = 1,400 sf / week

Production time = 3 days x 10 bays = 3.3 modules x 700 sqft / 5 days = 2,310 sf / week

Long module production @ Metric Modular, USA, slide 39
Slide 39 of 86Enlarge
Read slide 39 as text

Long module production @ Metric Modular, USA

Short module production @ Aprao, UK, slide 40
Slide 40 of 86Enlarge
Read slide 40 as text

Short module production @ Aprao, UK

Speed / Movement Impact:, slide 41
Slide 41 of 86Enlarge
Read slide 41 as text

Speed / Movement Impact:

Fast Production on Long lines = Modules have to move more often

Line indexing interval for 2 modules week: 40 hours, 10 bays traversed = 4 hour interval

Line indexing interval for 3.3 modules week: 40 hours, 10 bays, = 2.5 hour interval

Line indexing interval for 2 modules week: 40 hours, 10 bays traversed = 4 hour interval

Line indexing interval for 3.3 modules week: 40 hours, 10 bays, = 2.5 hour interval

More Moves = More production time consumed in movement, slide 42
Slide 42 of 86Enlarge
Read slide 42 as text

More Moves = More production time consumed in movement

Line indexing interval for 3.3 modules week: 40 hours, 10 bays, = 2.5 hour interval

Indexing time = 10 minutes x 2.5 = 32 minutes / shift = 6% of production time

30 bays x 4 day dwell = 7.5 modules / day

Indexing time = 10 minutes x 7.5 = 75 minutes / shift = 15% of production time

Dwell Time Impact: Line cannot move faster than the most time-consuming module, slide 43
Slide 43 of 86Enlarge
Read slide 43 as text

Dwell Time Impact: Line cannot move faster than the most time-consuming module

Mixing WC / Kitchen / shaft modules with living room modules = all slow

Separating module lines by complexity speeds production of simpler modules

Time to extract module from line = 20 minutes, slide 44
Slide 44 of 86Enlarge
Read slide 44 as text

Time to extract module from line = 20 minutes

Dwell = 4 days = 32 hours = 1% of production time

Static Bays: No module movement during production = Minimal moving time impact BUT a large space impact

Static Line Impact: Note amount of assembly space that cannot be occupied

Methods of module movement are dependent on the factory building and material handling equipment installed, slide 45
Slide 45 of 86Enlarge
Read slide 45 as text

Methods of module movement are dependent on the factory building and material handling equipment installed

Overhead crane allows “leapfrogging”

Wide bay allows transverse movement

Narrow bay requires longitudinal movement

Methods of movement: SmartHome Lateral rails, slide 46
Slide 46 of 86Enlarge
Read slide 46 as text

Methods of movement: SmartHome Lateral rails

Inverted wheels on floor!, slide 47
Slide 47 of 86Enlarge
Read slide 47 as text

Inverted wheels on floor!

Longitudinal movement on surface mount rails

Omnidirectional movement on Air Bearings

Factory_OS, slide 48
Slide 48 of 86Enlarge
Read slide 48 as text

Factory_OS

Leapfrogging

Static bay production @ FEWA PAD, ON, CAD, slide 49
Slide 49 of 86Enlarge
Read slide 49 as text

Static bay production @ FEWA PAD, ON, CAD

Transporter combined with a shipping gantry allows direct, right-off-the-line shipment of any module at any time, slide 50
Slide 50 of 86Enlarge
Read slide 50 as text

Transporter combined with a shipping gantry allows direct, right-off-the-line shipment of any module at any time

Prework, slide 51
Slide 51 of 86Enlarge
Read slide 51 as text

Prework

Prework

Prework

Prework

Prework

Prework

Tool carts, airlines and worker circulation

An ideal assembly line is: fed by sub-factories, dense, short, lateral and quickly produces a wide / long product

Catwalk Above

Inbound Materials

Outbound Modules

ADMIN

Offline production of partitions with upright buffering stands and pre-installed lifting eyes, slide 52
Slide 52 of 86Enlarge
Read slide 52 as text

Offline production of partitions with upright buffering stands and pre-installed lifting eyes

Pre-cut material cutting, inspection and kitting, slide 53
Slide 53 of 86Enlarge
Read slide 53 as text

Pre-cut material cutting, inspection and kitting

Offline sub-factory production of, slide 54
Slide 54 of 86Enlarge
Read slide 54 as text

Offline sub-factory production of

high-spec commercial pipe strings

Complex plumbing completed in <10% of, slide 55
Slide 55 of 86Enlarge
Read slide 55 as text

Complex plumbing completed in <10% of

Site-built hours

Offline floor and ceiling assembly and finishing, slide 56
Slide 56 of 86Enlarge
Read slide 56 as text

Offline floor and ceiling assembly and finishing

Completed panels rolled in on worktables (single handling) and tilted up, slide 57
Slide 57 of 86Enlarge
Read slide 57 as text

Completed panels rolled in on worktables (single handling) and tilted up

Most wood modular plants move and buffer wall panels vertically and assemble them to make a volume at a later point in t, slide 58
Slide 58 of 86Enlarge
Read slide 58 as text

Most wood modular plants move and buffer wall panels vertically and assemble them to make a volume at a later point in the production process

Components are welded together to make a 3D frame, which is then fit out in the plant to make a module., slide 59
Slide 59 of 86Enlarge
Read slide 59 as text

Components are welded together to make a 3D frame, which is then fit out in the plant to make a module.

ISO Containers are sometimes used.

Unitarily welded “chassis“

This approach means that the number of welders that can work simultaneously (human or robotic), is limited., slide 60
Slide 60 of 86Enlarge
Read slide 60 as text

This approach means that the number of welders that can work simultaneously (human or robotic), is limited.

Completed work is stranded as “Work In Process Inventory” while the rest of the chassis is welded.

Completed, but stranded = WIP

Accessible, but arc-on-time limited

Automated frame production time = length of weld x speed of welding / 4 robots = approx. 4 hours including loading and u, slide 61
Slide 61 of 86Enlarge
Read slide 61 as text

Automated frame production time = length of weld x speed of welding / 4 robots = approx. 4 hours including loading and unloading of fixture

Form impact: Unitary 3D frame production is slow

whether automated or not

Worse still, a unitarily-welded frame creates both a production bottleneck and unnecessarily difficult tasks such as ins, slide 62
Slide 62 of 86Enlarge
Read slide 62 as text

Worse still, a unitarily-welded frame creates both a production bottleneck and unnecessarily difficult tasks such as installing drywall overhead

Slide 63, slide 63
Slide 63 of 86Enlarge
A recent NA press release boasted that the cost of an automated wood modular plant with capacity of 2,000 modules / annu, slide 64
Slide 64 of 86Enlarge
Read slide 64 as text

A recent NA press release boasted that the cost of an automated wood modular plant with capacity of 2,000 modules / annum ( 166 / month) was $100m

Cost of $100m in CAPEX / month @6% over 8 years = $1,314,143.02 / month / 166 = $7,916 /CAPEX / module for frame production only (cost does not include OPEX such as maintenance, programming, etc………..)

Comparison: Cost of 240 hours labour for production of a mid-grade module @ $30 / hr = $7,200 / module for 100% of module = YIKES!

Automation actually increased the cost while replacing inexpensive labour with expensive, hard to find, highly-skilled technicians

Cost of Automation Per Module Produced

Bolted components trade expensive welds for fast, inexpensive bolts, slide 65
Slide 65 of 86Enlarge
Read slide 65 as text

Bolted components trade expensive welds for fast, inexpensive bolts

Welding of components = more arc-on time / less WIP and can be done with multiple / inexpensive COBOTS, slide 66
Slide 66 of 86Enlarge
Read slide 66 as text

Welding of components = more arc-on time / less WIP and can be done with multiple / inexpensive COBOTS

Frame kit production time = length of weld x speed of welding / 42 robots = approx. 6 minutes takt time / frame kit + 6 , slide 67
Slide 67 of 86Enlarge
Read slide 67 as text

Frame kit production time = length of weld x speed of welding / 42 robots = approx. 6 minutes takt time / frame kit + 6 unskilled labour hours for assembly

4 hours vs. 6 minutes = frame production speed improvement of 40x

Form impact: 1D frame component production with bolted assembly is highly scalable and up to 40x faster than unitary welding

Weld hours = 20, slide 68
Slide 68 of 86Enlarge
Read slide 68 as text

Weld hours = 20

Weld cost = $750

Assembly hours = 6

Assembly cost = <$300

FYI: Welding automation requires full properties of members and welds to be defined in 3D space, together with welding p, slide 69
Slide 69 of 86Enlarge
Read slide 69 as text

FYI: Welding automation requires full properties of members and welds to be defined in 3D space, together with welding parameters such as position, penetration, etc.

A kit frame ships to modular plants at the highest value density, slide 70
Slide 70 of 86Enlarge
Read slide 70 as text

A kit frame ships to modular plants at the highest value density

= lowest cost

Up to 18 frames / 40’ ISO container = <$250 ea. for trans-continental shipping

Screwing and nailing bridges work in the same way to multiply active tools, reducing takt time and WIP compared to one-a, slide 71
Slide 71 of 86Enlarge
Read slide 71 as text

Screwing and nailing bridges work in the same way to multiply active tools, reducing takt time and WIP compared to one-at-a-time fastening processes (Triad Mfg.)

The optimum sequence of volumetric assembly is critical:, slide 72
Slide 72 of 86Enlarge
Read slide 72 as text

The optimum sequence of volumetric assembly is critical:

Parts » Volumes » Fitout = creates the Ship-in-a-bottle” effect

Components » Volumes » Fitout = still a “Ship-in-a-Bottle”

Work completed but not moving =

“In Process Inventory”

Components » Panels » Fitout » Volumes = “Panelization”

Multiple processes simultaneously = “Arc-On Time” enhanced

Some plants……good and bad, slide 73
Slide 73 of 86Enlarge
Read slide 73 as text

Some plants……good and bad

3D Panelization Factory Planning Existing Building

SBGRPD Jeddah, KSA

2D Panelization Factory Workflow, slide 74
Slide 74 of 86Enlarge
Read slide 74 as text

2D Panelization Factory Workflow

Modular Factory Layout, slide 75
Slide 75 of 86Enlarge
Read slide 75 as text

Modular Factory Layout

in Existing 3-Bay Building

Panels-to-Volumes workflow is not ideal in a parallel-bay plant, as space, time and labour is lost to inter-bay transfers

There are many less parts in a module than a car., slide 76
Slide 76 of 86Enlarge
Read slide 76 as text

There are many less parts in a module than a car.

And excess movement eats in to production time.

So….the ideal assembly line is not unnecessarily long.

To increase volume, duplicate side-fed lines and / or establish specialized lines

And consider new geographies!

A multi-line,, slide 77
Slide 77 of 86Enlarge
Read slide 77 as text

A multi-line,

(clockwise) configuration provides 3 assembly lines moving at different speeds with JIT delivery directly to the line from on-site sub-plants, which receive materials at one end and feed subassemblies directly to the assembly lines at the other end.

Truck traffic is smooth, material handling is minimized and crossing paths are eliminated.

The concept applied to a US industrial park site with road access on one long side, slide 78
Slide 78 of 86Enlarge
Read slide 78 as text

The concept applied to a US industrial park site with road access on one long side

The sub-factory concept applied to an existing masonry building with a $%#@& floor plan, slide 79
Slide 79 of 86Enlarge
Read slide 79 as text

The sub-factory concept applied to an existing masonry building with a $%#@& floor plan

Summary: Product Design Impacts on Productivity, slide 80
Slide 80 of 86Enlarge
Read slide 80 as text

Summary: Product Design Impacts on Productivity

Module complexity / affects speed of completion

3 days to completion vs. 6 + days = 2 x output

Module quality / affects value of product

$20,000 vs. $70,000 / module = 3.5 x value output

Module completeness / affects value of product

$70,000 vs. $90,000 / module = 1.3 x output

Summary cont…., slide 81
Slide 81 of 86Enlarge
Read slide 81 as text

Summary cont….

Number of module variants / affects cost of design

5%-10% vs. <1% of project value = negative Δ $5,000+ / module

Module Size / Affects output psm of factory space /

35 sm vs. 60 sm / module = 2 x output / movement

Structural concept / affects production rate /

70k sm / annum vs. 140k sm / annum = 2x output

Summary cont…., slide 82
Slide 82 of 86Enlarge
Read slide 82 as text

Summary cont….

Size of plant / affects capacity

Linear relationship

Material handling methods / affects % wasted time

Range of effects to 3x

Density of product layout / Affects % wasted space

Range of effects to 1.5x

Summary cont…., slide 83
Slide 83 of 86Enlarge
Read slide 83 as text

Summary cont….

Effectiveness of automation / affects realized cost savings (loss)

Range of effects from – 2x to +10x (poorly conceived automation can actually be slower and more expensive than a manual operation)

Assembly methods / Affects “arc-on” time, reduces WIP / stranded production / reduces dwell times

Range of effects to 40x

Cashflow heaven exists…..it’s, slide 84
Slide 84 of 86Enlarge
Read slide 84 as text

Cashflow heaven exists…..it’s

a factory that runs like this:

Day 1: Material arrives

Day 2: Sub-assemblies produced

Day 3: Module assembled

Day 4: Module completed

Day 5: Module ships

Day 6: Module stacked

Day 7: Invoice submitted

Day 14: Labour paid for

Day 29: Material paid for

To achieve high volumes and retain ownership of your company:, slide 85
Slide 85 of 86Enlarge
Read slide 85 as text

To achieve high volumes and retain ownership of your company:

Initiate DfMAD

Achieve modest volumes

Satisfy customers profitably

Refine the product

Perfect the process

Achieve 7 days to invoicing

Add staff and capacity

Repeat

Thank you!, slide 86